Because the 12 months winds to an in depth, the Florida Division of Transportation (FDOT) can boast of great progress in 2024 on all three challenge corridors within the huge and impactful I-395/SR 836/I-95 Design-Construct Challenge in Miami.
The $818 million enterprise is the product of a partnership between FDOT and the Higher Miami Expressway Company and its contractor, the Archer Western – de Moya Group Joint Enterprise.
In an e mail to Miami At the moment, Oscar Gonzalez, senior neighborhood outreach specialist for the challenge, wrote: “On the east finish of the challenge on I-395, a number of site visitors shifts had been accomplished to open further areas for the development of the foundations for 2 of the six Signature Bridge arches in addition to to proceed the set up of precast arch segments on the tallest arch, which is able to soar 330 toes within the air and is situated east of Biscayne Boulevard adjoining to North Bayshore Drive.
“This 12 months additionally noticed the completion of one of many arches over Northeast Second Avenue, and only recently, all 41 precast, 90-ton arch segments had been erected for a second arch. Completion of the second arch, situated over Northeast Second Avenue, is anticipated early subsequent 12 months when the contractor will connect the 2 sides of the arch construction with a cast-in-place concrete pour,” wrote Mr. Gonzalez.
Later this 12 months, the final main concrete pour will happen on the large heart pier assist construction, the place all six arches will converge, he mentioned.
The sweeping building contains the Signature Bridge over Northeast Second Avenue and Biscayne Boulevard, an higher deck of site visitors constructed over State Street 836 and the Miami River, and the addition of 1 lane to the northbound entrance to I-95.
The general purpose is so as to add capability, improve the circulate of site visitors and security, and enhance entry alongside I-395, SR 836 and I-95.
Mr. Gonzalez reviews the outdated I-395 bridges have been demolished west of the Signature Bridge from Northeast First Avenue to west of Northwest Third Avenue in Overtown.
Eradicating the bridges has allowed crews to start the set up of auger forged piles and establishing foundations and piers for the brand new, higher-capacity I-395 mainline bridges.

The purpose of the large challenge is so as to add site visitors capability, improve circulate and security and enhance entry.
The contractor is scheduled to begin erecting the precast roadway segments for the brand new mainline bridges in mid-December.
Mr. Gonzalez famous that under the brand new I-395, an idea plan has been adopted for the 33 acres of neighborhood areas. FDOT and the Metropolis of Miami are working collaboratively on the ultimate design of the neighborhood areas that might be constructed as a part of the challenge, he mentioned.
Mr. Gonzalez mentioned, “This 12 months, the Metropolis of Miami was awarded a $60.3 million US Division of Transportation Reconnecting Communities and Neighborhoods Program Grant that can assist fund lots of the facilities that residents and guests will get pleasure from.”
Deliberate facilities embrace interactive water options, an amphitheater, a canine play space, play areas, 15 acres of city gardens, a one-mile central promenade, and lots of others, he mentioned.
His newest e mail provides extra particulars on the standing of the work:
This 12 months additionally noticed completion and closing acceptance of the concrete alternative work on I-95 from Northwest seventeenth Road to Northwest twenty ninth Road.
Work has been considerably accomplished on the southern finish from Northwest seventeenth Road to Northwest Eighth Road. The contractor is presently changing the site visitors railing alongside northbound I-95 between Northwest Eighth Road and north of Northwest 14th Road.
Over I-95, crews have accomplished the erection of the concrete bridge beams for the brand new westbound I-395 ramp to southbound I-95. Crews are making ready the ramp for the concrete pour for the deck, which would require partial and full nighttime closures of each northbound and southbound I-95.
Work on SR 836 has additionally progressed steadily, with a concentrate on basis work.
This 12 months, crews accomplished all of the foundations, together with two drilled shaft foundations within the Miami River from Northwest seventeenth to twelfth avenues and all of the set up of augur forged piles from Northwest twelfth Avenue to I-95.
All of the piers west of Northwest twelfth Avenue, besides one on the Richard Gerstein Justice Constructing parking space, have been accomplished. Crews are engaged on basis and pier building east of Northwest twelfth Avenue.
The 488-foot cap and beam lifter is presently working east of Northwest seventeenth Avenue, erecting bridge caps and beams requiring partial and full closures of SR 836 between Northwest seventeenth and twelfth avenues.
Simply west of the interchange, an enormous bridge assist construction spanning the entire eastbound SR 836 lanes and the ramps to northbound and southbound I-95 was poured out this 12 months utilizing 47 concrete vans.
Mr. Gonzalez mentioned with Miami Artwork Week in full swing, the challenge staff is adjusting work schedules and lane closure instances to accommodate the patrons attending the Artwork Week occasions.
Whole challenge completion is focused for late 2027.